Load an Import File with Multiple Projects Concurrently

Run the Integration Wizard to load an import file with multiple projects concurrently.

Attention:
  • Deltek recommends that PM Compass users only use this dedicated queue for Cobra processing.
  • Make sure that your environment is set up to run multi-project concurrent integration. See Multi-Project Concurrent Integration.

To load an import file with multiple projects concurrently:

  1. Click the Integration tab.
  2. In the Import group, click File.
  3. On the Integration Configuration page, click Open an existing configuration to load an existing configuration, or click Create a new configuration to create a new one (for example, a budget configuration).
  4. On the Project Selection page, select a valid import file with multiple projects, and select the Defined in File checkbox.
    Attention: For more information, see Import File with Data from Multiple Projects.
  5. Click Next and complete the succeeding pages of the Integration Wizard-Scheduling Tools and Files.
  6. On the Save and Load page, click Load data now? and Send to process server.
  7. Click Finish.
    When the integration completes successfully without errors, click View Log to display the master process log that contains entries of the overall multi-project integration as well as the details of each job.
    Attention: For details on possible errors and fixes, see View Job Status and Process Logs and Troubleshooting Concurrency Issues.